A work is completed by A, B and C in 15 days 12 days and 20 days respectively. If they together earn Rs.4800 for the whole work .What is the earning of C?

1
Rs. 1200
2
Rs. 600
3
Rs. 800
4
Rs. 400
5
Rs. 1000