A is 50% more efficient as B. In one day, C can do half of the work done by A and B together. If C alone can do the work in 40 days, then A, B, and C together can do the work in how many days?
1
44/3 days
2
43/3 days
3
41/3 days
4
40/3 days
5
50/3 days