4 persons can complete a piece of work in 12 days. If work needs to be completed in 8 days, the minimum number of persons required will be:
1
5
2
6
3
10
4
12
4 persons can complete a piece of work in 12 days. If work needs to be completed in 8 days, the minimum number of persons required will be: