state gov Maharashtra Town Planning Assistant (TPA) Test Series 2024 Construction Materials and Management Project Planning PERT
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
1
50%
2
Less than 50%
3
More than 50%
4
100%