state gov Maharashtra Zilla Parishad Supervisor, Sr. Assistant & EO Mock Test 2023 Quantitative Aptitude Time and Work Work Efficiency
Ram completes 1/7 parts works in 2 days. Shyam completes 3/7 parts of work in 5 days. Remaining parts of work is done by Ajay. Find the work done by Ajay in percentage.
1
66.67%
2
85.70%
3
64.26%
4
42.85%
5
21.42%