state gov Maharashtra Zilla Parishad Jr. Assistant, Steno & Ringman Mock Test 2023 Quantitative Aptitude Time and Work
15 men can complete a piece of work in 20 days. After how many days should 10 men join the work so that the whole work is completed in 14 days?