state gov TSPSC Polytechnic Lecturer Mock Test 2022 Industrial Engineering Production Planning and Inventory Control Aggregate Production Planning and Scheduling
The observed time for an element is 0.7 minutes, The rating factor is 90%. All the allowances put together are 20% of normal time .Calculate the Standard time in minutes.
1
0.756
2
0.856
3
0.5
4
2.0