state gov AP Police SI (Pre+Mains) Mock Test 2022 Quantitative Aptitude Time and Work Work Efficiency
A and B together can complete a work in 20 days. B and C together can complete the same work in 24 days. The work was started by A and he works for 8 days, then after B works for 11 days and C completes the remaining work in 22 days. The number of days required for C alone to complete the work is
1
40
2
36
3
34
4
32