state gov MP Vyapam Group 4 (AG III & Steno) Mock Test Series 2025 Quantitative Aptitude Time and Work Work Efficiency
A work can be completed by 18 boys in 24 days. If 6 boys leave after working for 12 days, then how many days will be needed to complete the remaining work?
1
12
2
15
3
18
4
24