A alone can complete a piece of work in 18 days and B alone can complete the same work in 24 days. A and B undertook the work for ₹22,500. They took the help of C and completed the work in 8 days. How much is to be paid to A?
1
₹5,192
2
₹10,000
3
₹9,000
4
₹7,500