A alone can complete a work in 8 days, while B alone can complete it in 10 days. If both of them work together to complete this work, then for this they get Rs. 900 as remuneration, Find the share of A and B respectively in this and also find in how many days it took to complete the work?

1
Rs. 400, Rs. 500, 40/9 days
2
Rs. 300, Rs. 600, 4 days
3
Rs. 600, Rs. 300, 4 days
4
Rs. 500, Rs. 400, 40/9 days