state gov APPSC Group 4 (Pre+Mains) Mock Test 2022 Quantitative Aptitude Time and Work Work Efficiency
N women can complete the project in 12 days. If 5 women are less employed then it will take 15 more days to complete the same project, then find the number of women initially employed.
1
9
2
15
3
12
4
24