A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. B and C together will complete \(\frac{5}{8}\)th part of the original work in:
1
15 days
2
10 days
3
18 days
4
12 days