state gov OSSSC RI, ARI, AMIN, SFS, ICDS Supervisor Combined Mock Test 2023-25 Quantitative Aptitude Time and Work
350 workers can do work in 60 days. It is decided to add some workers just to end the work 4 days before of scheduled time. How many should more workers be added?
1
60
2
25
3
55
4
75