A alone can complete a work in 10 days and B can complete it in 15 days. A and B undertake the work for Rs. 4,800. With the help of C, they complete the work in 5 days. What amount is to be paid to C?

1
Rs. 700
2
Rs. 1200
3
Rs. 800
4
Rs. 600