state gov Patna High Court Mazdoor (Group C) Mock Test 2025 Quantitative Aptitude Time and Work Work Efficiency
36 men can complete a bridge in 12 days. Four days after they started working, 14 more men joined them. How many days will they now take to complete the remaining work?
1
5.6 days
2
6.7 days
3
5.8 days
4
4.5 days