state gov Chandigarh Police Constable Mock Test 2023 Quantitative Aptitude Time and Work Work Efficiency
P, Q and R together can do a piece of work in 56 days. P and Q together can do one-fourth as much work as R alone. In how many days can P and Q together complete the entire work?
1
140
2
70
3
280
4
210