SSC Delhi Police Constable 2025 Mock Test Series (New) Quantitative Aptitude Time and Work Work Efficiency
If 330 persons can complete the construction of a shopping complex in 50 days, how many persons are required to complete the same work in 30 days?
1
505
2
198
3
450
4
550