Suhani and Sneha working together can finish a project in 16 days. If Sneha alone can do the same work in 44 days, then in how many days Suhani can complete the work?

1
20 days
2
25\(\frac{1}{4}\) days
3
25 days
4
25\(\frac{1}{7}\) days