To estimate the cost of whole project by detailed estimate, provision for supervision (or) departmental charge is:

1
10 % to 15 % of the estimated cost
2
1.5 % to 2 % of the estimated cost
3
3 % to 5 % of estimated cost
4
15 % to 20 % of estimated cost