defence exam Indian Coast Guard Assistant Commandant (GD/CPL) 2025 Test Series Quantitative Aptitude Time and Work Work Efficiency
A can do a piece of work in 12 days. B can do that work in 36 days. After working together for 3 days, B left the job. In how many days can A complete the remaining work?
1
6
2
12
3
8
4
24