defence exam Indian Navy Fireman/Fire Engine Driver Mock Test 2024 Quantitative Aptitude Time and Work Work Efficiency
10 men can complete a work in 5 days and 10 women take 10 days to complete the work. How many days will 5 men and 6 women take to complete the work?
1
\(7 \frac{1}{4}\) days
2
\(6 \frac{1}{4}\) days
3
\(7 \frac{1}{2}\) days
4
None of these