defence exam ITBP Constable (Animal Transport) Mock Test 2024 Quantitative Aptitude Time and Work Work Efficiency
40 men can complete a piece of work in 6 days. In how many days will 36 men complete the same work?
1
\(6 \frac{2}{3}\)
2
\(7 \frac{2}{3}\)
3
\(8 \frac{3}{4}\)
4
\(8 \frac{2}{3}\)