Among the following, the correct sequence of WBM construction will be:

i. Preparation of subgrade

ii. Spreading of Coarse aggregates

iii. Application of binding material

iv. Application of screenings

v. Provision of lateral confinement

1
i, ii, iv, iii, v
2
i, iv, ii, iii, v
3
i, v, ii, iv, iii
4
ii, i, iv, v, iii