engineering recuitment NFC Chemical Plant Operator Mock Test Quantitative Aptitude Time and Work Work Efficiency
A can do 75% of a job in 24 days and B can do half of the job in 4 days. If they work on it together in how many days can they the job?
1
12. 8
2
9.6
3
6.4
4
10.2