engineering recuitment Punjab SSSB Jr Draftsman Civil Mock Test 2021 Quantitative Aptitude Time and Work Work and Wages
X, Y and Z completed a work costing Rs. 4,480. X worked for 4 days, Y for 6 days and Z for 8 days. If their daily salary is in the ratio 5 : 6 : 7, then how much money will X get?
1
Rs. 800
2
Rs. 1200
3
Rs. 2400
4
Rs. 3000