When float or slack of an activity is positive: 

1
it represents a situation where extra resources are available and the completion of project is not delayed
2
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
3
the activity is critical and any delay in its performance will delay the completion of whole project
4
None of the given options