engineering recuitment DDA JE Civil 2023 Mock Test Irrigation Engineering Water Requirement of Crops
What will be the delta for a crop when its duty is 864 hectares/cumec on the field if the base period of this crop is 120 days?
1
100 cm
2
120 cm
3
432 cm
4
None of these