engineering recuitment DDA JE Civil 2023 Mock Test Quantitative Aptitude Time and Work Work Efficiency
A is 30% more efficient than B. How many days will it take them to combine the work that A alone could have done in 23 days?
1
11 days
2
13 days
3
15 days
4
17 days