Fill in the blank with the correct option:
Shuttering of beams spanning over 6 m should be removed in ________ .
1
10 days
2
21 days
3
5 days
4
7 days
5
18 days
Fill in the blank with the correct option:
Shuttering of beams spanning over 6 m should be removed in ________ .