Security deposit deducted at 5% from contractors’ bills is:
1
Refunded when the contractor completes the work
2
Refunded even before the completion of the work provided good progress has been established.
3
Retained till the expected life of the structure and spent for maintenance.
4
Refunded when the defect liability period of six months or one monsoon whichever is later is over.