engineering recuitment Vizag Steel MT Mechanical 2020 Test Series Industrial Engineering Production Planning and Inventory Control Line Balancing and Work Study
The standard time of an operation has been calculated as 10 min. The worker was rated at 80%. If the relaxation and other allowances were 25%, then the observed time would be :
1
12.5 min
2
10 min
3
8 min
4
6.5 min