engineering recuitment Vizag Steel MT Mechanical 2020 Test Series Industrial Engineering Operations Research Queueing Theory
If average arrival rate in a queue is 6/hr and the average service rate is 10/hr, which one of the following is the average number of customers in the line, including the customer being served?
1
0.3
2
0.6
3
1.2
4
1.5