engineering recuitment Vizag Steel MT Mechanical 2020 Test Series Industrial Engineering Production Planning and Inventory Control Line Balancing and Work Study
What is the cycle time in a line balancing problem?
1
It is equal to station time
2
It is equal to the time required to complete one set of a job
3
It is greater or at least equal to maximum station time
4
It is minimum of all the station time