The following data were obtained from testing a 48 kVA, 4800/240 V, 50 Hz transformer.

OC test from LV side

240 V

2 A

120 W

SC test from HV side

150 V

5 A

60 W


The maximum efficiency (in %) of the transformer 0.707 lagging power factor load is ________ (up to two decimal places)

Enter numerical value using the virtual keypad. Round off where necessary.