SSC Supreme Court Junior Court Assistant Mock Test Series 2025 Quantitative Aptitude Time and Work Work Efficiency
Abha can do some work in 10 days, Billu can do it in 20 days and Chintu can do it in 40 days. They start working in turns with Abha starting to work on the first day followed by Billu on the second day and by Chintu on the third day and again by Abha on the fourth day and so on, till the work is completed fully. Find the time taken (approx.) to complete the work fully.
1
16 days
2
17 days
3
15 days
4
20 days