engineering recuitment UPMRC JE 2024 Mock Test Power Systems Economies of Power Generation Diversity Factor
A generating station is to supply four regions of load whose peak loads are 15MW, 10MW, 14MW & 18MW. The diversity factor at the station is 1.9 and the average annual load factor is 60%. What is the maximum demand on the station?
1
30 MW
2
38 MW
3
48 MW
4
25 MW