Which of the following is not a valid reason to prepare a revised estimate?

1
When a sanctioned estimate is likely to exceed by more than 5% due to structural alteration.
2
When the expenditure of works exceeds by more than 10% of the administrative approval.
3
When there are material deviations from the original proposal.
4
When it is found that the sanctioned estimate is more than the actual requirement.