engineering recuitment UPCL AE (E&M) 2021 Mock Test Quantitative Aptitude Time and Work Work Efficiency
Printer A and Printer B can print 1800 saree working 8 hrs in 5 days. Printer A can print as many Sarees in 3 hrs as Printer B can print in 2 hrs. How many saree can Printer B print in 1 hour?
1
18
2
27
3
30
4
21