engineering recuitment KPSC Assistant Engineer Civil Mock Test 2020 Construction Materials and Management Project Planning PERT
Calculate the earliest expected time (in days) and latest allowable occurrence time (in days) respectively for the event F for the following network.
1
15 and 21
2
15 and 26
3
21 and 21
4
21 and 26