The purpose of work-break-down structure in project planning is mainly to

1) Facilitate and improve the decision-making on procurement of resources .

2) Relate activities under particular trade specializations to help in organizing for project staff

3) Co-ordinate regarding milestone events across trade specialization to improve the synergy between the trades

1
1 and only 
2
1 and 3 only 
3
2 and 3 only 
4
1, 2 and 3