engineering recuitment WBPSC JE Civil Mock Test 2022 Construction Materials and Management Estimation and Costing
In case of bids in Two-Envelop System, the correct option is
1
Technical bid is opened first
2
Either of the two (Technical and Financial) bids can be opened first
3
Both (Terminal and Financial) bids are opened simultaneously
4
Financial bid is opened first