engineering recuitment BARC Stipendiary Trainee Category I 2023 Mock Test Irrigation Engineering Diversion Headworks
At a certain point in the floor of wier, the uplift pressure head due to seepage is 4.8 m. If the relative density of concrete is 3.4, then the minimum thickness of floor required at this point to counteract the uplift pressure (without FOS) will be
1
1 m
2
2 m
3
2.67 m
4
4 m