With reference to Planning, identify the CORRECT statements.
1. Dummy activity maintains the logical interrelationship between different activities.
2. Dummy activity keeps the numbering system of the network unique.
3. Dummy activity is a resource oriented activity.
1
1 and 2
2
2 and 3
3
1, 2 and 3
4
1 and 3