engineering recuitment TSPSC AEE Civil Mock Test 2022 Construction Materials and Management Project Planning
Which of the following statements is INCORRECT with respect to the calculation of LST (Latest Start Time) for the activities involved in a network diagram?
1
At the end event LST is equal to Zero
2
The calculation of LST starts from end event
3
The computations are done through backward pass method
4
The computations of LST usually proceeds right to left