Consider the following statements:
1. In a work-breakdown structure top down approach is adopted.
2. Bar chart depicts interdependencies of activities.
3. Controlling can be better achieved in milestone chart.
Which of these statements is/are correct?
1
1 and 3 only
2
1 and 2 only
3
2 and 3 only
4
1, 2 and 3