Which of the following statement(s) is/are correct regarding software project management?
I. PERT charts can be derived automatically form Gantt charts.
II. Gantt charts cannot be automatically derived from PERT charts.
1
Only I
2
Neither I nor II
3
Both I and II
4
Only II
5
Question Not Attempted