Which of the goals are essential when conducting risk reassessment in software project management?
A: To identify risks that have been eliminated due to completed project phases.
B: To adjust the ranking of risks based on new developments or uncovered information.
C: To disregard previous risk assessments and start a new risk analysis from scratch.
D: To finalize the project schedule without making further adjustments for risks.