Kamal and Vimal can do piece of work in 12 days, Vimal and Bharat in 15 days and Bharat and Kamal in 20 days. If Kamal, Vimal and Bharat work together, in how many days will they complete the work?

1
12 days
2
10 days
3
15 days
4
16 days