engineering recuitment OSSC Combined Technical Services (ଓଡିଶା) Mock Test 2023-24 Estimating, Cost and Valuation Measurement
The 'centre line method' is specially adopted for estimating?
1
Circular buildings
2
Other geometrical shaped buildings
3
Hexagonal buildings
4
all of these